CSX Remains Unclear About Future of Carolina Connector | Eastern NC Now

While state officials say they are not aware that CSX has changed its plans to build a $272 million rail hub in Edgecombe County, a company spokesman says new leaders at the rail giant are reviewing all planned projects

ENCNow
    Publisher's note: This post was created by the staff for the Carolina Journal, John Hood Publisher.

State has spent more than $4 million preparing for rail hub


    While state officials say they are not aware that CSX has changed its plans to build a $272 million rail hub in Edgecombe County, a company spokesman says new leaders at the rail giant are reviewing all planned projects.

    The state has spent more than $4 million of the proposed $100 million taxpayer incentive on the Carolina Connector project.

    In an email, CSX spokesman Rob Doolittle told Carolina Journal the company would not definitively say the rail hub would be completed:

  • In an effort to enhance CSX's operating performance, provide a superior service product for our customers and create value for shareholders, CSX's new leadership team is conducting a comprehensive, strategic review of all aspects of our business, including our intermodal business and existing and planned infrastructure projects. Intermodal service will remain an important part of CSX's business. Any changes will be communicated directly with CSX customers and other stakeholders.
  • CSX appreciates the partnership we have developed with the State of North Carolina and we look forward to continuing the dialogue with the State about the Carolina Connector (CCX) and our plans moving forward.

    A report last week from the trade website Train News Wire said the project near Rocky Mount was dead.

    "The developments are part of CEO E. Hunter Harrison's drive to improve efficiency and profitability," Train News Wire said.

    Meantime, NCDOT spokesman Steve Abbott says, to his knowledge, the project is on track. In an email, Abbott said:

  • We are not aware that CSX has canceled the project. To date, NCDOT has spent $4,316,057.27 for preliminary engineering to include required studies and design work. If needed, the state would exercise its authority to be reimbursed.
  •     A CJ review of Edgecombe County property records shows CSX has acquired the land necessary for the project.

        Check back with CarolinaJournal.com for updates.
Go Back


Leave a Guest Comment

Your Name or Alias
Your Email Address ( your email address will not be published )
Enter Your Comment ( text only please )




State Superintendent Provides $30 Million in School Construction Grants from Lottery Money Carolina Journal, Editorials, Op-Ed & Politics Supreme Court Decisions Defy Simplistic Partisan Spin


HbAD0

Latest Op-Ed & Politics

Democrat-run states have said they won’t send official delegations to the country’s 250th birthday bash
The North Carolina House unanimously passed the “Dominique Moody Safety Act,” advancing a child-welfare reform package named for the six-year-old girl whose death exposed repeated failures by Mecklenburg County social services officials to act on reports of abuse and neglect.
Maybe a holiday for Texas, but NOT the nation

HbAD1

government agencies refused to help on fear of being called "racist"
targets data centers and intermittent electricity sources

HbAD2

5 year sentence for failing to cooperate with surveillance of cit citizens
"He is fully fit to carry out all duties of the Commander-in-Chief and Head of State."
illegal alien "asylum seeker" migrants are a crime wave on both sides of the Atlantic

HbAD3

 
 
Back to Top